Ntui–Ndjole Road: 8.041% of Works Completed with Delays Noted in the Execution Schedule

Posté le : nov. 28, 2022, Par : alima - Dans : Actualités

The weekly assessment made on 19 November 2022 by the project Control Mission states that the execution of works relating to the resumption of the Ntui-Ndjole road development project (60 km), including 73 km of council roads, is experiencing a significant delay compared to the projected schedule.

Whilst works completion rate stands just at 8.041% including 13.04% for earthworks, the time frame has already been consumed at 53.33%. On the field, the asphalt plant is being installed; the installation of the equipment is ongoing, including the assembly of the plant, the assembly of the bitumen preparation system (bitumen boiler, emulsion plane), the installation of the hydrocarbon product distribution piping and the installation of the controlling cabin. Out of the 81 structures projected on this 60-km-long route, five of them are being constructed, out of which four have been completed and are pending adjacent backfilling.  In this regard, it should be noted that the construction of hydraulic works is still facing difficulties due to the low mobilisation of human resources and a shortfall in the supply of prefabricated pipe culverts components, which were produced in Obala and have been delivered since 14 November 2022. For their part, stripping works have recorded better progress in the field, though there are also delays as regards the relocation of graves found along the rights-of-way between KP 39+275 and 39+600.

In general, works progress rate on the field remains quite low. The delays noted are more acute as concerns the execution of hydraulic works and pavement layers (improved subgrade and sub-base), which require additional equipment. Regarding the financial situation of the project, the invoices submitted amount to 8,580,464,972 CFA francs, representing 28.88% of the entire cost, with 7,086,016,283 CFA francs as start-up advance; the invoice for works No.1 is 536,707,760 CFA francs, that of Works No. 2 stands at 249,069,982 CFA francs, and 398,991,046 CFA francs for invoice No.3. The invoice for works No. 4, which stands at 309,679,901 CFA francs, is pending signature. An invoice for penalties, amounting to 70,860,163 CFA francs including taxes, was also issued.

The resumption of development works for the Ntui - Ndjole road (60 km) and 73 km of council roads was awarded to China Railway 20 Bureau Group Corporation for an amount exclusive of taxes of 29,710,760,098 CFA francs and 7,216,175,454 CFA francs respectively. The control and supervision of these works was assigned to CIRA S.A/ BEC LA ROUTIERE SARL joint venture.

Plus de contenus dans Actualités

Travaux en régie sur la N5, 80 dégradations traitées au 4 mai 2023

Posté le : mai 5, 2023, Par : alima - Dans : Actualités


Les équipes de la Brigade nationale des Travaux en régie et des services déconcentrés compétents du Minist...

Réhabilitation de la route Mora-Dabanga-Kousséri (205 km).

Posté le : janv. 20, 2017, Par : admin - Dans : Actualités

Le cadre de politique de réinstallation vient d’être publié dans la rubrique documen...

Région du Littoral : démarrage des travaux de cantonnage sur l’axe Bekoko-Pont du Moungo.

Posté le : mars 28, 2024, Par : BEYOKOL - Dans : Actualités

Le Délégué Régional des Travaux Publics pour la région du Littoral a procédé le lundi, 18 mars 2024, au lancem...

Reconstruction de la route Babadjou-Bamenda: les travaux de la voie de contournement de Bamenda sont exécutés à 17%

Posté le : mai 5, 2023, Par : alima - Dans : Actualités

Ces travaux exécutés par l’entreprise Bofas s’étendent sur un linéaire de 4.9 km partant de Welcome to Bamend...

North Region: Construction of bridge over Mayo Pintchoumba river ongoing

Posté le : févr. 15, 2024, Par : BEYOKOL - Dans : Actualités

The construction of the bridge over River Pintchoumba in the North Region is ongoing. In this month of February 2024,...

Compteur de Visites : sbar Visite(s)

Evènements & Chantiers

» Etude des normes sur les ralentisseurs de vitesse de la signalisation horizontale.

Le Ministre répond à vos questions

La question du jour
En quelle année la loi portant protection du patrimoine routier a t-elle été adoptée?

Suivez-nous sur les réseaux sociaux - FaceBook Twitter RSS