North Region: Construction of bridge over Mayo Pintchoumba river ongoing
Posté le : févr. 15, 2024, Par : BEYOKOL - Dans : Actualités
The construction of the bridge over River Pintchoumba in the North Region is ongoing. In this month of February 2024, the physical progress Works is overall 45,26%, as concern the ingenieurs.
The project is part of contract N°117/M/MINMAP/CMPM-TI/2019 of June 24, 2019, awarded to a Joint venture consteuction company ARMADA - CAM SARL /ARMADA - TCHAD SARL. The execution of the construction of the bridge and its access points over the Mayo Pintchoumba river is at PK 11+800 on the Pana Poli road section, in the Faro division, of the North Region. It is awarded to SARL/ CADEK SARL. While specifying the development of an infrasteucture, the physical progress of work as of now stands at 45.24%. What has been done so far starts from the site installation, clearing the rights side way and the general earthworks the development of the roadway.The execution of construction works of a bridge over the Mayo Pintchoumba river is financed by the Public Invested Budget (PIB) for an estimated amount of 2 144 131 913 including tax. According to the construction work schedule, the completion of work is plannes for the 23 of December 2024. But in the meantime, what is left on the field on done is the casting of deck, the embankment adjacent to the road, the implementation of rehabilitation, the completion of the supersteuctures such as , (sidewalk, wearing course, safety barriers and road and sidewalk seal) and the development of access road. The completion of the construction work of the bridge with access road aims at restore communication between the cities of Pana and Poli to open up production areas, by improving the tansportation of goods and persons leading to the development of economic activities thereby increase income, also facilitate access to markets, hospitals and schools.
Plus de contenus dans Actualités
Aménagement de la route Ntui – Ndjole, l’entreprise a entamé les travaux liés à la couche de forme
Posté le : mai 13, 2022, Par : alima - Dans : Actualités
Le projet concerne l’aménagement d’un linéaire de 60 km de route en béton bitumineux de 5 cm d’épaisseur en...
129e édition de la fête internationale du travail au MINTP : aboutissement des grands chantiers dans la paix et la sécurité
Posté le : mai 8, 2015, Par : admin - Dans : Actualités
C’est tout en sons et couleurs que le 1er mai 2015, le personnel du Ministère des travaux publics (MINTP)...
Réhabilitation de la Nationale N9, Mbalmayo-Sangmélima: un procédé nouveau pour l’exécution des travaux
Posté le : juil. 27, 2022, Par : alima - Dans : Actualités
Le Ministre des Travaux publics effectue ce jour, 25 juillet 2022, un parcours de l’itinéraire du projet de réhab...
Aménagement du corridor Bamenda-Mamfe-Ekok : plusieurs routes aménagées dans la région du Nord-Ouest
Posté le : oct. 31, 2022, Par : alima - Dans : Actualités
Le pont sur la Cross-river et les aménagements sociaux et économiques symbole la concrétisation des engagements du...