North-west: Maintenance of some major roads in the western network
Posté le : oct. 31, 2014, Par : Hannah - Dans : Actualités
Transformation in high gear, this project is no longer a dream but a reality that has taken shape and is impacting on the economy of the area.
The road which is within the framework of a joint Cameroon-Nigeria project, code named, Nkambe-Berabe-Ako (D74), Ako-Abongsie border to Nigeria (7D4), Misaje border with Nigeria (D105) and Kakar-towards Adamawa Region (P26). The multinational road and transport facilitation programme seeks to maintain the 153 km road from Cameroon to Nigeria borders which will boost relationships and socio-economic ties between the two countries.
The physical work done on the site is about 80%, as indicated by the engineers executing and controlling the project. According to the engineers of ETS SAWI Company, in charge of the execution of the project and CERBAT the company carrying out control, the first phase of the 153 km maintenance road project is progressing and preparatory works are ongoing on the second and third phase. The contract was awarded under No 135/M/MINTP/CPM-ERRP/2010. The road maintenance project that is at least 153km long has been split into four lots;
- Lot 1; Nkambe-Berabe-Ako (D74)
- Lot 2; Ako-Abongsie border to Nigeria (7D4)
- Lot 3; Misaje border with Nigeria (D105) and,
- Lot 4; Kakar-towards Adamawa Region/NW (P26)
The maintenance work is contracting for specific items of maintenance work, such as the resealing, overlay or reconstruction of a specific length of pavement are widely used and there is considerable experience. However, particularly for road maintenance works, there is often a need for contracts to cover a wider scope of work. Routine and periodic maintenance operations are sometimes contracted separately. Walls of the loose soils surrounding the road are being reinforced with concrete.
Plus de contenus dans Actualités
SECOND PONT SUR LE WOURI : LES TRAVAUX ATTEIGNENT 30% DE REALISATION
Posté le : nov. 5, 2014, Par : admin - Dans : Actualités
C’est au cours de la visite de chantier effectuée le 30 octobre 2014 par le chef service du marché du seco...
PONT SUR LE NTEM : L’INSTALLATION ET LA VALIDATION DES ETUDES POURRAIENT ACCELERER LES TRAVAUX
Posté le : juil. 25, 2014, Par : Hannah - Dans : Actualités
Un pont de 2x1 voie sur la rivière Ntem est en cours de construction. Ce pont qui es...
Route Mandjou-Akokan, les travaux vont s’achever en décembre 2021
Posté le : nov. 4, 2021, Par : alima - Dans : Actualités
Travaux en régie sur la N5 : 502 dégradations déjà traitées
Posté le : mai 16, 2023, Par : alima - Dans : Actualités
Route Léna-Nsegbe-Tibati: un cas d’école avec des économies réalisées chiffrées en Milliards de francs.
Posté le : avril 2, 2020, Par : alima - Dans : Actualités
Les travaux de construction de la route Léna-Nsegbe-Tibati (135,16km) s’exécutent de manière satisfai...