North-west: Maintenance of some major roads in the western network
Posté le : oct. 31, 2014, Par : Hannah - Dans : Actualités
Transformation in high gear, this project is no longer a dream but a reality that has taken shape and is impacting on the economy of the area.
The road which is within the framework of a joint Cameroon-Nigeria project, code named, Nkambe-Berabe-Ako (D74), Ako-Abongsie border to Nigeria (7D4), Misaje border with Nigeria (D105) and Kakar-towards Adamawa Region (P26). The multinational road and transport facilitation programme seeks to maintain the 153 km road from Cameroon to Nigeria borders which will boost relationships and socio-economic ties between the two countries.
The physical work done on the site is about 80%, as indicated by the engineers executing and controlling the project. According to the engineers of ETS SAWI Company, in charge of the execution of the project and CERBAT the company carrying out control, the first phase of the 153 km maintenance road project is progressing and preparatory works are ongoing on the second and third phase. The contract was awarded under No 135/M/MINTP/CPM-ERRP/2010. The road maintenance project that is at least 153km long has been split into four lots;
- Lot 1; Nkambe-Berabe-Ako (D74)
- Lot 2; Ako-Abongsie border to Nigeria (7D4)
- Lot 3; Misaje border with Nigeria (D105) and,
- Lot 4; Kakar-towards Adamawa Region/NW (P26)
The maintenance work is contracting for specific items of maintenance work, such as the resealing, overlay or reconstruction of a specific length of pavement are widely used and there is considerable experience. However, particularly for road maintenance works, there is often a need for contracts to cover a wider scope of work. Routine and periodic maintenance operations are sometimes contracted separately. Walls of the loose soils surrounding the road are being reinforced with concrete.
Plus de contenus dans Actualités
Route Babadjou-Bamenda: les travaux sont exécutés à 8,5% sur la section Babadjou-Matazem
Posté le : juin 2, 2022, Par : alima - Dans : Actualités
La réunion mensuelle du projet tenue le 02 juin 2022 dans les locaux de la mission de contrôle, a permis d’...
Autoroute Yaoundé-Douala, phase 1: le MINTP apprécie l’évolution des travaux sur les voies de raccordement
Posté le : nov. 10, 2023, Par : BEYOKOL - Dans : Actualités
Autoroute Yaoundé-Douala (Phase I). On indemnise les riverains entre le PK10 et le PK 20
Posté le : mars 23, 2016, Par : Hannah - Dans : Actualités
Les riverains victimes d’expropriation entre le PK10 et le PK20 de l’auto...
Discours du Président de la République, S.E.M. Paul BIYA, lors de la cérémonie de pose de la première pierre des travaux de construction du deuxième pont sur le Wouri à Douala, le 14 novembre 2013
Posté le : nov. 26, 2013, Par : mesp23 - Dans : Actualités
Monsieur le Président du Sénat,
•Monsieur le Président de l'Assemblée Na...
Coopération : la Directrice et représentante de l'UNOPS chez le Ministre des Travaux Publics.
Posté le : mai 11, 2022, Par : alima - Dans : Actualités
Mme Tatiana WAH, Directrice et représentante du Bureau des Nations Unies pour les Services d'Appui aux Projets...